Is it paying twice?
69 of the 982 sites we checked in five states already have a charger, put up before PM E-DRIVE: 58 in Kerala, 6 in Rajasthan, 5 in Uttar Pradesh. We did not check Odisha or Vadodara. The question is whether FAME II already paid for them.[1]
- Sites with an existing charger
- 69
Does the charger next door work?
181 of the 1,180 sites have a public charger within 500 metres.[1] What matters is who runs it, and whether it works.
Can the public get in?
MHI's rules say every site should be open to the public without restriction, whatever its category.[7] We sorted each site by what it is. Offices, colleges and venues such as stadiums are likely to open only in office hours. Substations, telephone exchanges, depots, parks and police stations see little coming and going, so a public bay at the gate should be easy to arrange; some Kerala substations already have public parking outside. Car parks, roadsides, bus stands, railway stations and hospitals are already open round the clock.[1]
- Likely open in office hours only
- 304 of 1,180
- Expected to be open round the clock
- 521
- of which substations
- 334
- Already open round the clock
- 355
Is it subsidising its own land?
Kerala's tender came from KSEB, the state power utility. 91 of its 209 sites are in substations or on KSEB offices or land.[1]